Measure J Project Schedules

Measure J Project Schedules Updated November, 2024

Current Projects

1. Renegade Athletic Complex

Construction Dates: January 2021 - December 2024

Current Phase: In Closeout

Description: Building a new gym and field house on the BC campus which will house a gymnasium, office spaces, classrooms, weight room, a field house, locker rooms, training rooms, and a fitness center.

The Swim Pool buildings were removed from the original project scope of work due to unforeseen conditions. Project is currently in redesign.

Program Value: $67.7 Million

Contractor: S.C. Anderson, Inc.

Architect: Cannon

2. Arvin General Education Center

Construction Dates: December 2022 - December 2024

Current Phase: In Closeout

Description: Building a new Bakersfield College satellite campus in the Arvin community. This will be a multi-use building with classrooms, offices, and other student services.

Program Value: $29.8 Million

Contractor/Project Manager: Colombo Construction Company, Inc. (CM@Risk)

Designer: IBI Group

3. Infrastructure

Construction Dates: Over the course of Measure J projects

Description: To improve the aging Bakersfield College campus, monies have been set aside for repairs/renovations. These repairs/renovations have been broken up into nine smaller projects.

Program Value: $15 Million

Completed projects:

  • Central Plant Complete
  • EMS system and building meters (water, gas, power) In Progress
  • Campus Water Upgrade/Sewer/Gas In Design
  • TES Tank Repair Complete
  • Math/Science Coil Replacement On Hold
  • Wrought Iron Perimeter Fence Project (School Farm) Complete
  • Wrought Iron Perimeter Fence Project (Edible School Yard Area) Complete

Potential Projects to Come

  • Campus High Voltage Electrical Systems
  • Security Cameras/Data/Fiber
  • Water Infrastructure

4. Agriculture

Construction Dates: October 2023 - February 2026

Current Phase: Construction

Description: Create an “Agricultural Quad” to house a single-story general agriculture building, greenhouses, a horticulture shop, and a mechanized agriculture show (ag 

mech).

Program Value: $60 Million

Current Phase: In Construction

Contractor/Project Manager: Colombo Construction Company, Inc. (CM@Risk)

Architect: Teter Architects

5. Delano Center Campus Monument Sign/Sidewalk and Landscape

Construction Dates: June 2024 - August 2025

Current Phase:  Construction

Program Value: $3.0 Million

Contractor/Project Manager: S&B Sons

Architect: AP Architects

 

6. New Student Housing

Construction Dates:  June 2024 - March 2026

Current Phase: In Construction

Program Value: $63 Million

Contractor: Bernards

Architect: PBK Architects

7. Center for Student Success

Construction Dates: TBD

Current Phase: Programming Completed. Matching funding from California State Capital Outlay Program. Measure 2 passed at the November 2024 election.

Program Value: $36 million

Contractor: TBD

Architect: TBD

8. Lab Tech Bachelors Program

Construction Dates: March 2024 - Dec 2024

Current Phase: Construction

Program Value: $2.3 Million

Contractor: JTS Construction

Architect: AP Architects

9. Science and Engineering Phase II

Construction Dates:  May 2024 - Jan 2025

Current Phase: Construction

Program Value: $1.5 Million

Contractor: Petra

Architect: PBK

COMPLETED PROJECTS

Delano Learning Center

Construction Dates: January 2022 - June 2023

Current Phase:  LRC Building complete and occupied.

Description: Create a Learning Resource Center on the Delano-Timmons campus to house new classrooms, a library, and offices, along with new landscaping. Project is DSA approved and will be closed out in FUSION by Dec 2024

Program Value: $26 Million

Contractor/Project Manager: Vanir, Inc. (CM@Risk)

Architect: Klassen

Science and Engineering Building

Construction Dates: December 2019 - August 2022

Description: New three-story Science and Engineering building to house offices, labs, and classrooms for the Science and Engineering department.

Program Value: $61.9 Million

Contractor: Bernards

Architect: HMC Architects

Administrative Services

Construction Dates: April 2021 - November 2022

Description: Renovation of the current bookstore and business services building to house College Safety, the Health Center, Marketing, Human Resources, Institutional Research and Financial & Administrative Services

Program Value: $7.6 Million

Contractor/Project Manager: McMurtrey Lince, Inc. - Multi-Prime Trades

Architect: Ordiz Melby Architects

Welcome Center

Construction Dates: April 2021 - September 2023

Description: Renovation of the current Administration Building to consolidate departments serving incoming student needs and act as a “one-stop shop”

Program Value: $9.5 Million

Contractor/Project Manager: McMurtrey Lince, Inc. - Multi-Prime Trades

Architect: Teter Architects

Campus Center - 3rd Floor Kitchen

Construction Dates: October 2022 - March 2023

Description: The complete buildout of a thermalization kitchen space adjacent to the Renegade Event Center to serve banquet needs

Program Value: $2 Million

Contractor/Project Manager: JTS Construction

Architect: PBK Architects

Wireless Infrastructure

Program Value: $2 Million

Construction Date: August 2018 - January 2020

Current Phase: Second phase of expanding access points

Description: Updating all external/green spaces with wireless access points

Contractor: Multiple Vendors