Planetarium Upgrade Original Timeline
(as of early May 2005)
- May 13: City
Transfer to remove the planetarium seating and store in the Huddle
- May 16: Ash
Enterprises to begin removal of dome and planetarium equipment and store
in the Huddle
- May 23June 3: Contractor
to begin asbestos abatement of fireproofing
- June 6: Start
of construction
- August 22: All
construction activities on the first floor to be completed
- October 31: Project
complete
- November 1-4: Install
seating
- November 7: Begin
installation of dome and equipment